Works include:
The removal of all mezzanine floors associated with the work stations created by the previous tenant
The removal of cladded walls, steel beams, plasterboard walls, ceilings, tea points, WC blocks, etc
The scaffold was erected to facilitate the removal of an atrium and subsequently replace with roof cladding
Structural columns removed from open areas and structural integrity boosted at roof level to improve space available
All new lighting, power, fire alarm provision and air conditioning throughout the warehouse area
Noise considerations with neighbouring offices and warehouse units
Restrictive access for deliveries and waste away managed on a day-to-day basis ensuring 48 hours notice provided to Site Management