Scaffold built up off level 6 rather than disturb street-level shops and businesses
Diversions of all existing rooftop plant and services, utilising temporary plant
Extending lift shaft up to new floor while maintaining one lift always running
Stair core extension opening up to the new floor and 2 new Passenger lifts, 1 also serving as a Fireman’s lift
Steel framed extension
Fully glazed exterior curtain walling to occupied spaces with two sets of bifold doors, leading onto terraces
Zinc cladding to all remaining structure
Completely new Plant and services in the relocated area serving the entire building
CAT B fit-out to new office space. inc glazed screens, feature wall panelling, kitchen and WC joinery
Resin flooring
Dry riser and upgraded stair core to create a Fire fighting stair